LAND DEVELOPMENT CONTROL COMMITTEE
MINUTES OF MEETING HELD ON 28th
OCTOBER 2002
|
|
PLANNING APPLICATIONS |
||||
|
|
Please note that the following
information clause is attached to the decision notice of all full building
applications that are approved with or without conditions. ¨ NB This permission does not in any way constitute a waiver of the
need to obtain building permission for this proposed development and any
other necessary Government licensees and or permits that may be required. The
applicant is responsible for obtaining all necessary licenses that may be
required. |
||||
|
|
2002/0256 Amendment to subdivision, Sandy Hill
(93315B/211, 212 and 214) Warwick Woods Butler
|
||||
|
|
Approved |
||||
|
|
2002/0290 Cinema ,retail and restaurant,
North Central (48713B/292) Brothers Auto Sales |
||||
|
|
Deferred for : |
|
|
||
|
|
1. |
Submission of a
statement of the proposed gross floorspace
and / or seating for each element of the proposal (i.e. retail
floorspace, cinema seating) |
|||
|
|
2 |
Submission of a
site plan to include the following: |
|||
|
|
|
a) |
A parking layout
that provides parking at least to the following ratio: ¨
1 car parking space
per 300 gross sqft of shop and or restaurant space
¨
1 car parking space
per 10 seats for the cinemas
¨
a designated loading
area for the shop units
The parking to
include accessible parking spaces for disabled people in accordance with
Appendix F of the Building Code |
||
|
|
|
b) |
A sewage package
treatment plant for the development |
||
|
|
|
c) |
On site soakaway
for stormwater |
||
|
|
3 |
Details of the
manner in which the single storey cinema will function i.e. indicative
seating layout |
|
|
4 |
Consideration by
the applicant to the relocation of the parking area and providing an entrance
at the northern section of the site to reduce any potential impact on traffic
flow on Edwin Wallace Rey Drive. This is further to the detailed discussions
between the agent (during week of 20th October 2002) and the
Department of Physical Planning. |
|
|
The applicant is also advised that if additional land is required at this stage to facilitate the above points (as was suggested by the agent) that they may wish to also consider any options that they may have for expansion of the proposed development in the future and that this be taken into consideration in the design and layout at this time. |
|
|
|
||
|
|
2002/0347 Pier, Island Harbour (89218B/94)
Peter Billington |
|
|
|
Refused for
the following reasons:
1. The proposed structure represents an
obstruction to free access along the foreshore and if permitted would be a
precedent for similar proposals, which would result in a detrimental effect on
the waterfront environment of Anguilla. 2. The development requires the
anchoring of a pier / jetty to existing coral in a reef system that is
already under serious stress. The development would lead to further
degradation of the reef system. 3. The proposal involves built
development on Crown Land for which permission has been sought but has been
denied for the reasons stated above. Note: The application
makes no mention of whether the jetty is to be accessed by boats. It should
be noted that if it is the following points should be noted: ¨
The sea ward
entrance to the proposal site is punctuated with high coral heads that will
make access to the proposed jetty / pier difficult and is likely to expose
the entire reef system in this area to damage from accidents resulting from
maneuvering of vessels. ¨
The Island
Harbour jetty facility was developed for the express purpose of providing a
safe docking area with limited negative impact upon the environment. This
proposal is in relatively close proximity to this facility and therefore an
alternative means of boat access is available. The applicant
is advised that whilst a right of appeal exists the Land Development Control
Committee and Ministry of Social Development and Planning consider that there
are no material or other factors that have changed since the dismissal of
previous planning appeals for jetty / pier proposal(s) at this site.
|
|
|
|
2002/0352 Advertisement, The Valley (48814B/191)
Frank Costin / Savannah Gallery
|
|
|
|
Deferred for
consultation with a Government agency.
|
|
|
|
2002/0357 Subdivision, Shoal Bay (59018B33) Albert
Lake
|
|
|
|
Approved |
|
|
|
2002/0370 Cellular Base Station and
Antenna, Corito (38812B/88) Cable & Wireless |
|
Approved subject to the following conditions:
|
1 |
All
antennas to be erected on the mast must be: |
||
|
|
a) |
Low
gain; |
|
|
|
b) |
Operated
in full compliance with the International
Commission on Non-Ionising Radiation Protection (ICNIRP) guidelines; |
|
|
|
c) |
Operated
within a radio frequency of 800-900 MHz; |
|
|
|
d) |
Produce
a plane wave power density of 0.0699 mW/cmsq or less. |
|
|
2 |
The
antennas shall not be used until the following have been submitted for
approval to the Ministry of Infrastructure Communication and Utilities (copy
to the Department of Physical Planning) : |
||
|
|
a) |
A
certificate stating that the equipment to be erected meets the International
Commission on Non-Ionising Radiation Protection (ICNIRP) guidelines for
limiting exposure to electromagnetic fields. |
|
|
|
b) |
A site plan clearly showing the maximum fields of
radiation including details of strength and frequency and that these do not
exceed 0.0699 mW/cm-sq. at 100 feet and the ICNIRP standards. |
|
|
|
c) |
A
signed declaration stating that radio
frequency fields will be kept as low as reasonably practicable at all times
and never exceed the ICNIRP
standard or 0.0699 mW/cm-sq. |
|
|
3 |
Annual
independent monitoring reports must be submitted to the Ministry of
Infrastructure Communications and Utilities every year relating to the levels
of radiation being emitted from the antenna. |
||
|
4 |
Approved
planning applications from other companies / organisations to mast share at
this site cannot be unreasonably withheld by the applicant and site operator.
|
||
|
5 |
Before
the erection of the tower / mast a security fence and gate must be fully
erected to ensure no trespass onto the site and to protect the public. |
||
|
6 |
Prior
to its erection the mast and tower should be painted and marked in accordance
with the requirements of the civil aviation authority and maintained in this
state. |
||
|
|
|
|
|
|
Information
Note: For
clarity on all matters relating to
the operation of this site, planning permission will be required for the: ¨ change of any antennas from low to
high gain; ¨ increase in number of antennas; ¨ increase to over 900 MHz in radio
frequency being operated; ¨ change in a plane wave power density
to over 0.0699 mW/cmsq. |
|||
|
|
2002/0371 Cellular Base Station and
Antenna, Blowing Point (38410B/9) Cable & Wireless |
|||
|
|
Deferred for a public meeting to be held |
|||
|
|
2002/0379 Subdivision, Sandy Ground
(08513B/127) Selena Lake- Richardson |
|
|
Approved with the following condition: This
approval in no way confers planning permission for the use of Lot 1 (the
remainder of the parcel for residential development). Such a proposal would
require separate planning approval. |
|
|
2002/0380 Grant of easement, Lockrum
(38510B/20) Preston Richardson |
|
|
Approved subject to the 12.5 ft right of way
across Block 38510B Parcel 20 and 21 being registered concurrently with the
12.5ft right of way over parcels 144,145,146,147,148 and 149 of Block 38510B |
|
|
2002/0381 Subdivision, The Quarter
(78914B/33) Victor Banks |
|
|
Deferred for the subdivision plan to show the
distance of all existing buildings from site boundaries and existing and
proposed rights of way. |
|
|
2002/0382 Subdivision, Old Ta (48613B/32)
Agnes Gumbs & David Reid Gumbs |
|
|
Approved. The
applicant was also advised that this site is within the designated airport
approach zone and that built development at the site (which requires separate
planning permission) must not exceed 35 feet in height from ground level. |
|
|
2002/0383 Subdivision, Rendezvous
(28009B/12) Jeremiah Gumbs |
|
|
Deferred for: i.
the
subdivision plan to be amended to show : a) the position of the existing coastal
vegetation line which is a requirement of coastal subdivisions. Visits to the
site have revealed that the line marked on the plan does not follow the
existing vegetation; b) a right of way serving the
development of a minimum width of 25 feet; ii.
the
submission of a detailed project description clearly indicating the proposed
land use of each Lot. This should include details of bedroom numbers etc. The
description should also indicate how the land is to be comprehensively
developed in a planned / phased rather to ensure that it is not piecemeal
manner. iii.
the
amendment of the description of the proposed subdivision on the application
form to take full account of point ii above. Note: The Land
Development Control Committee has an established and published policy that
development must be setback a minimum of 100 feet from the landward side of
the coastal vegetation line at this beach. Whilst it is difficult for the
Committee to consider the impact of this setback on all proposed lots given
the absence of clear information (as highlighted in point 1 a) above) it may
prevent the development in the manner suggested of a number of lots (for
example Lot 13). In any development
scheme the planning of a comprehensive sewage treatment facility rather than
separate individual systems should be considered. The applicant to note that the established density policy for tourism development is between 10 and 30 bedrooms per acre this should be fully considered in the subdivision proposals for this site. |
|
|
2002/0384 Cellular Base Station and
Antenna, Long Path (69114B/24) Cable & Wireless |
|||||
|
|
Deferred for public consultation and press
notices. |
|||||
|
|
2002/0385 Cellular Base Station and
Antenna, White Hill (89418B/74) Cable & Wireless |
|||||
|
|
Deferred for public consultation and press
notices. |
|||||
|
|
2002/0386 Dwelling House, Shoal Bay
(59018B/35) Simon Hemans |
|||||
|
|
Approved. |
|||||
|
|
2002/0387 Dwelling House, Cannifist &
Chalvilles (89216B/174) Julet Simon |
|||||
|
|
Approved. |
|||||
|
|
|
|||||
|
|
2002/0388 Dwelling House, South Hill
(38511B/71) Julian Hughes |
|||||
|
|
Approved. |
|||||
|
|
2002/0389 Dwelling House, Big Bottom
(58816B/233) Kharim Walters |
|||||
|
|
Approved. |
|||||
|
|
2002/0390 Dwelling House, Sandy Hill (79214B/193)
Justin Richardson |
|||||
|
|
Approved. |
|||||
|
|
2002/0391 Dwelling House, Old Ta
(48613B/170) Marlene Lewis |
|||||
|
|
Approved. |
|||||
|
|
2002/0392 Dwelling House, South Hill
(18010B/105) James Rochester |
|||||
|
|
Deferred for the proposal to show setbacks
that are at least the minimum required by the Land Development Control
Committee (i.e. 16 feet from all right of ways, 16 feet from back boundary
and 6 feet from side boundary). All distances to be measured from the closest
point of the built development. |
|||||
|
|
2002/0393 Two additional apartments, South
Hill (28211B/125 lot 4) Benjamin Carty |
|||||
|
|
Refused for the following reasons: 1. The development would result in a density level (33 dwelling units per acre) considerably in excess of the Anguilla’s established levels of between 9 to 12 dwelling units per acre. This would result in an over-intensive development that is also inconsistent with the densities in the neighbourhood. 2. The development by virtue of it’s
over-intensive design would result in an unsatisfactory level of amenity for
existing and future occupiers of the site and neighbouring land. 3. The parking spaces that are proposed
are below the minimum required width of 8 feet. These would create inadequate
manoeuvring space and be unsatisfactory. |
|||||
|
|
Note: The applicant
was also advised that the Registered Subdivision held at the Department of
Lands and Surveys states a maximum Lot width of 69 feet. The submitted
drawing indicates 72 feet.
|
|||||
|
|
2002/0394 Dental suite, Shoal Bay (89118B/36) Samuel
Mason
|
|||||
|
|
Deferred for : i.
consultation
with Government agencies ii.
submission
of a floorplan showing the existing and proposed layout; iii.
identification
on the site plan of designated parking for staff and patients of the proposed
dental suite. |
|||||
|
|
2002/0395 Yacht club, jetty and moorings, Cul-de-sac
(28309B/48) Gianfranco Comparetti
|
|||||
|
|
Deferred for : |
|||||
|
|
1. |
The site plan to be
amended to include: |
|
|
||
|
|
|
|
a) |
Sewage package
treatment plant and indication of how this relates to the wider site sewage
systems. Distances from all existing and proposed buildings must be provided. |
||
|
|
|
|
b) |
A designated
parking area for the yacht club spaces at a ratio of not less than 1 space
per 300 gross sqft of floorspace. The site plan should clearly indicate the
areas of parking that have been approved for existing built development and
the areas that are proposed for other future development (if any). |
||
|
|
|
|
c) |
Designated area for
the storage of garbage and other solid waste |
||
|
|
|
|
d) |
Distances of the
yacht club building from existing approved and built structures |
||
|
|
|
|
e) |
Method of stormwater
collection and a drainage scheme for the development this should clearly show
contours and drainage ‘falls’. Should the applicant wish this can be
submitted on a separate contoured drainage plan (which must indicate location
of sewage package system and buildings as a minimum) |
||
|
|
|
|
f) |
Location of any
services for the ‘jetty’. For example piped water, electricity, disposal of
waste oil etc. A technical data sheet and detailed drawing will also be
required for such facilities. |
||
|
|
|
|
g) |
Location of
pump-out facilities for dealing with the sewage and wastewater from yachts
using the moorings and jetty. A technical data sheet and detailed drawing
will also be required for such facilities. Facilities for washing down and
emptying portable toilets may also be required. |
||
|
|
2 |
|
The map showing the
proposed position of moorings to include: |
|||
|
|
|
|
a) |
Distance of closest
mooring(s) from beach and high water marks |
||
|
|
|
|
b) |
Bathymetric survey
to include any designated approach channels to the moorings and to the jetty.
This should provide information on the below water bottom contours. The
depths to be shown as smooth contours. The datum should be clearly labeled on
the plan. |
||
|
|
|
|
c) |
Survey data on
marine vegetation i.e. extent and type (sea grass beds, coral etc). This
should include the area adjacent to the proposed jetty. |
||
|
|
3 |
|
The drawing for the
jetty (including section through) to clearly show: |
|||
|
|
|
|
a) |
the location of all
services being provided for example piped water, electricity, waste oil etc.
Details of emergency shut off facilities for each service will also be
required |
||
|
|
|
|
b) |
the location of all
navigational / warning lighting (if proposed to be affixed to the jetty |
||
|
|
|
|
c) |
A detailed section
of method of fixing piles to the earth (this should be a constructional / engineering
drawing) |
||
|
|
|
|
In
the meeting held with the Department of Physical Planning on 28th
October mention was made of removal blow out panels or similar to reduce risk
of damage from ground seas and hurricanes. This or an alternative option is
recommended to be used for the jetty and should be clearly annotated on the
drawings. |
|||
|
|
4 |
|
The
method of mooring to include details of at surface markers and methods of
limiting anchor and chain drag and consequent scouring of sea bed or marine
vegetation. |
|||
|
|
5 |
|
Preparation
of a comprehensive development plan of the yacht club and mooring development
and all the up land supporting facilities that are planned / required for the
area – i.e. all facilities that are necessary to make the development viable. |
|||
|
|
6 |
|
Consultation
with Government agencies |
|||
|
|
7 |
|
Radio
announcement and public consultation |
|||
|
|
The Applicant was
also advised of the following: |
|||||
|
|
As
highlighted by the Department of Physical Planning during the week of 20th
October and 28th October 2002 to the agent, the results of the
consultation and response to the above issues will assist in the ‘scoping’ of
the project. This will help to determine the extent / content of any
Environmental Impact Assessment (EIA) that is required for the project. As
such the applicant should be fully aware that further details (potentially
including an EIA) may be required by the Committee to make a full
determination of the application. At
this stage two of the key issues that has been highlighted are: a)
method of
sewage disposal and proposed management and enforcement arrangement to ensure
that sewage and waste water is not discharged from vessels or the development
into the sea b)
method of
piling for the pier and the location of the mooring ‘blocks’ and their
relationship with the marine vegetation / coral / reef etc. This
information is offered to assist the agent and applicant and does not in any
way limit the Committee from raising other issues at a subsequent time. The
Committee would also like the applicant to consider the ‘upland’ use of the
site with respect to its relationship with a yacht club of this scale. For
example whether any other facilities are to be provided such as showers,
laundry services, larger restaurant or recreational facilities. |
|||||
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|